Fix first. Likely A/E return: Revise and Resubmit. The lintel finish and bollard pipe schedule don't match the spec, the roof ladder is missing its sealed delegated-design calcs, and two required product data sheets are missing. Several 'by others' notes also push scope back that the spec assigns to this section.
Projected readiness if the items in each step are fixed. Work the steps in order: blockers first.
| # | Location | Issue | What to change |
|---|---|---|---|
| 1 | p.3, Sheet D1 | Lintels L1-L6 shown as shop primed only (shown but wrong). (2.5.A) | Please change the lintel finish to hot-dip galvanized per ASTM A123, since these sit in exterior walls. |
| 2 | p.4, Sheet D2 | Bollard pipe shown as Schedule 40 (shown but wrong). (2.2.B) | Please revise bollards to ASTM A53 Gr B Schedule 80 pipe. |
| 3 | p.5, Sheet D3 | Roof ladder delegated-design calculations are missing. (1.3.C, 2.1.A) | Please include the ladder calculations signed and sealed by a PE licensed in the project's state. |
| 4 | Product data | Shop primer and galvanizing repair paint product data are missing. (1.3.A) | Please add product data for the shop primer and the ASTM A780 galvanizing repair paint. |
| # | Location | Issue | What to change |
|---|---|---|---|
| 5 | p.2, Sheet E1, Note 4 | 'All dimensions field verify' is used in place of contract document dimensions. (Core rule 3) | Please remove the blanket field-verify note and dimension from the contract documents; call out any specific conflicts separately. |
| 6 | p.2, Sheet E1, Note 6 | Overhead door embeds and anchor bolts marked 'furnished and installed by others' (scope gap). (2.6.A) | The spec has this section furnishing these items for the concrete trade to install. Please show them as furnished by Acme. |
| 7 | p.4, Sheet D2 | Bollard concrete fill marked 'by others' (scope gap). (3.1.A) | The spec includes concrete fill and crowned tops in this section. Please update the note. |
| 8 | p.6, Sheet D4 | Field touch-up marked 'by others' (scope gap). (3.1.B) | Field touch-up of primer and galvanizing is part of this section. Please update the note. |
| 9 | Package | Welding certificates are missing. (1.4.A) | Please include current welding certificates with the package. |
| 10 | p.3-6 | Anchorage details for lintels, bollards and ladder are not shown. (1.3.B) | Please add anchorage/embedment details for each item. |
| Article | Requirement | Status | Location | Note |
|---|---|---|---|---|
| 1.3.A | Product data: post-installed anchors | OK | p.1 | Hilti KB-TZ2 stainless with ESR included. |
| 1.3.A | Product data: nonshrink grout | OK | p.1 | Sika Grout 212 included. |
| 1.3.A | Product data: shop primer | MISSING | No primer product data in the package. | |
| 1.3.A | Product data: galvanizing repair paint | MISSING | No galvanizing repair (ASTM A780) product data. | |
| 1.3.B | Shop drawings with plans, details, connections, anchorage, weld symbols | WRONG | p.2-6 | Plans and details shown; anchorage details for bollards, ladder and lintels not shown. |
| 1.3.C | Roof ladder delegated design, signed and sealed by licensed PE | MISSING | p.5, Sheet D3 | Sheet says 'Design by fabricator. (No calculations included.)' |
| 1.4.A | Welding certificates | MISSING | Not included. | |
| 2.2.A | Plates, shapes, bars ASTM A36 | OK | p.3, Sheet D1 | Lintels called out A36. |
| 2.2.B | Bollard pipe ASTM A53 Gr B, Schedule 80 | WRONG | p.4, Sheet D2 | Schedule 40 shown. |
| 2.2.C | Tubing ASTM A500 Gr C | OK | p.5-6 | Ladder rails and door framing A500 Gr C. |
| 2.3.A | Stainless torque-controlled expansion anchors with ICC-ES report | OK | p.1 | |
| 2.5.A | Exterior items (lintels in exterior walls, bollards, ladder) hot-dip galvanized ASTM A123 | WRONG | p.3, Sheet D1 | Bollards and ladder OK; lintels shown shop primed only. |
| 2.5.B | Interior items shop primed | OK | p.6, Sheet D4 | |
| 2.6.A | Furnish anchor bolts and embed plates for overhead door supports | WRONG | p.2, Note 6; p.6 | Shops say furnished and installed by others. |
| Item | Shown on submittal | Furnished by (spec) | Installed by | Gap? |
|---|---|---|---|---|
| Overhead door embed plates and anchor bolts p.2, Sheet E1, Note 6 | Furnished and installed by others | This section (05 50 00), per 2.6.A | Section 03 30 00 (concrete), per 1.1.B | Gap |
| Bollard concrete fill p.4, Sheet D2 | Concrete fill by others | This section, per 3.1.A | This section, per 3.1.A | Gap |
| Field touch-up of primer and galvanizing p.6, Sheet D4 | Field touch-up by others | This section, per 3.1.B | This section, per 3.1.B | Gap |
| Item | Spec requires | Shown | Location |
|---|---|---|---|
| Lintels L1-L6 in exterior walls | Hot-dip galvanized after fabrication, ASTM A123 (2.5.A) | Shop primed, gray | p.3, Sheet D1 |
| Issue | Location | CD reference |
|---|---|---|
| General Note 4 says 'All dimensions field verify prior to fabrication.' Use the contract document dimensions; only raise specific conflicts. | p.2, Sheet E1, Note 4 |
OneRound pre-flight reports are a pre-submission quality check prepared for the submitting trade. They are not an approval, an engineering review, or a substitute for review by the Architect/Engineer of record. Generated 2026-10-19.