Sample from a fictional test package. View each level:Report $35Roadmap $79Ready-to-Send $149Check your own submittal free →
Open the sample markup set
OneRound Pre-Flight Review  |  Sample Project (fictional test case 01)
Metal Fabrications Shop Drawings 05 50 00-01
Spec Section 05 50 00 Metal Fabrications - Roadmap Report
Rev 010/20/2026
ProjectSample Project (fictional test case 01)Spec Section05 50 00 Metal Fabrications
Submittal No.05 50 00-01Submittal TypeShop Drawings + Product Data
Submitted ByAcme Misc Metals (fictional)Supplier / RepNot shown on package
ManufacturersHilti (anchors); Sika (grout)Architect / EngineerNot shown on package
Review LevelRoadmap ReportPackage6 pages, every page reviewed
Prepared ForSubmitting tradeReport ID00000000

1. Review Verdict

Fix first
Fix first: 4 blockers would likely draw a Revise and Resubmit

The lintel finish and bollard pipe schedule don't match the spec, the roof ladder is missing its sealed delegated-design calcs, and two required product data sheets are missing. Several 'by others' notes also push scope back that the spec assigns to this section.

Likely A/E return as submitted: Revise and Resubmit
28/100
Likely kickback
Likely Revise and Resubmit

2. What This Package Submits

Shop drawings and product data for the Section 05 50 00 metal fabrications: exterior lintels L1-L6, pipe bollards B1-B8 at the loading dock, roof ladder RL-1, and overhead door jamb and header supports OD-1/OD-2. Steel is submitted per Article 2.2, post-installed anchors and grout per 2.3, and finishes per 2.5.

#ComponentManufacturer / ModelKey DataPkg Pages
ALintels L1-L6L6x4x3/8, ASTM A36Bearing 8 in. each end; finish shown shop primed3
BPipe bollards B1-B86 in. dia. pipe, ASTM A53 Gr B Sch 404'-0" exposed; hot-dip galvanized ASTM A1234
CRoof ladder RL-1HSS side rails ASTM A500 Gr C; 3/4 in. rungs at 12 in. o.c.Hot-dip galvanized; delegated design5
DOverhead door supports OD-1/OD-2HSS jamb and header framing, ASTM A500 Gr CInterior; shop primed6
EPost-installed anchorsHilti KB-TZ2 stainless expansion anchorICC-ES report attached1
FNonshrink groutSika Grout 2121

3. Specification Compliance at a Glance

6Complies
0Exceeds spec
4Revise
4Missing
0To confirm
4Blockers
6Fixes
0Notes
3Scope gaps

14 spec requirements checked against all 6 pages of the package.

4. Your Roadmap to the Stamp

Today
28/100
Current readiness
▶
Step 1
76/100
Clear 4 blockers
▶
Step 2
97/100
Make 6 fixes
▶
Step 3
Re-check and send
One round to the stamp

Projected readiness after each step. Work top to bottom: blockers first. Item numbers match the numbered clouds in your markup set.

Step 1 - Clear the blockers (each one alone would likely draw a Revise and Resubmit)

#SeverityLocationIssueWhat to changeOwner
1BLOCKERp.3, Sheet D1Lintels L1-L6 shown as shop primed only (shown but wrong).
Ref: 2.5.A
Please change the lintel finish to hot-dip galvanized per ASTM A123, since these sit in exterior walls.Detailer
2BLOCKERp.4, Sheet D2Bollard pipe shown as Schedule 40 (shown but wrong).
Ref: 2.2.B
Please revise the bollards to ASTM A53 Gr B Schedule 80 pipe. If Schedule 40 is intended, declare it as a deviation on the cover sheet with the reason so the architect can rule on it.Detailer
3BLOCKERp.5, Sheet D3Roof ladder delegated-design calculations are missing.
Ref: 1.3.C, 2.1.A
Please include the ladder calculations signed and sealed by a PE licensed in the project's state.Engineer of record
4BLOCKERProduct dataShop primer and galvanizing repair paint product data are missing.
Ref: 1.3.A
Please add product data for the shop primer and the ASTM A780 galvanizing repair paint.Supplier / rep

Step 2 - Fix before sending (likely to be noted by the A/E)

#SeverityLocationIssueWhat to changeOwner
5FIXp.2, Sheet E1, Note 4'All dimensions field verify' is used in place of contract document dimensions.
Ref: Contract documents
Please remove the blanket field-verify note and dimension from the contract documents; call out any specific conflicts separately.Detailer
6FIXp.2, Sheet E1, Note 6Overhead door embeds and anchor bolts marked 'furnished and installed by others' (scope gap).
Ref: 2.6.A
The spec has this section furnishing these items for the concrete trade to install. Please show them as furnished by Acme.Project manager
7FIXp.4, Sheet D2Bollard concrete fill marked 'by others' (scope gap).
Ref: 3.1.A
The spec includes concrete fill and crowned tops in this section. Please update the note.Project manager
8FIXp.6, Sheet D4Field touch-up marked 'by others' (scope gap).
Ref: 3.1.B
Field touch-up of primer and galvanizing is part of this section. Please update the note.Project manager
9FIXPackageWelding certificates are missing.
Ref: 1.4.A
Please include current welding certificates with the package.Project manager
10FIXp.3-6Anchorage details for lintels, bollards and ladder are not shown.
Ref: 1.3.B
Please add anchorage/embedment details for each item.Detailer

5. Work Plan, Page by Page

Open your markup set next to this list. Each block is one page of your submittal; each number is the cloud on that page.

Page 1 · Cover, contents and product data list
4
Shop primer and galvanizing repair paint product data are missing.
→ Please add product data for the shop primer and the ASTM A780 galvanizing repair paint.
Product data · Ref 1.3.A · Supplier / rep
9
Welding certificates are missing.
→ Please include current welding certificates with the package.
Package · Ref 1.4.A · Project manager
Page 2 · Sheet E1 Erection Plan
5
'All dimensions field verify' is used in place of contract document dimensions.
→ Please remove the blanket field-verify note and dimension from the contract documents; call out any specific conflicts separately.
p.2, Sheet E1, Note 4 · Ref Contract documents · Detailer
6
Overhead door embeds and anchor bolts marked 'furnished and installed by others' (scope gap).
→ The spec has this section furnishing these items for the concrete trade to install. Please show them as furnished by Acme.
p.2, Sheet E1, Note 6 · Ref 2.6.A · Project manager
Page 3 · Sheet D1 Lintels
1
Lintels L1-L6 shown as shop primed only (shown but wrong).
→ Please change the lintel finish to hot-dip galvanized per ASTM A123, since these sit in exterior walls.
p.3, Sheet D1 · Ref 2.5.A · Detailer
10
Anchorage details for lintels, bollards and ladder are not shown.
→ Please add anchorage/embedment details for each item.
p.3-6 · Ref 1.3.B · Detailer
Page 4 · Sheet D2 Bollards
2
Bollard pipe shown as Schedule 40 (shown but wrong).
→ Please revise the bollards to ASTM A53 Gr B Schedule 80 pipe. If Schedule 40 is intended, declare it as a deviation on the cover sheet with the reason so the architect can rule on it.
p.4, Sheet D2 · Ref 2.2.B · Detailer
7
Bollard concrete fill marked 'by others' (scope gap).
→ The spec includes concrete fill and crowned tops in this section. Please update the note.
p.4, Sheet D2 · Ref 3.1.A · Project manager
Page 5 · Sheet D3 Roof Ladder
3
Roof ladder delegated-design calculations are missing.
→ Please include the ladder calculations signed and sealed by a PE licensed in the project's state.
p.5, Sheet D3 · Ref 1.3.C, 2.1.A · Engineer of record
Page 6 · Sheet D4 Overhead Door Supports
8
Field touch-up marked 'by others' (scope gap).
→ Field touch-up of primer and galvanizing is part of this section. Please update the note.
p.6, Sheet D4 · Ref 3.1.B · Project manager

6. Markup Legend

Red revision cloud = Blocker. Fix before sending.
Orange revision cloud = Fix. Likely noted by the A/E.
Gray revision cloud = Note. Good practice.
#Numbered bubble = roadmap item number. Every cloud is also listed in your Bluebeam Markups List with the issue and the fix.

7. Hand-Off Lists by Owner

Send each person only their items. Numbers match the roadmap and the clouds.

Detailer 4 items
1. Please change the lintel finish to hot-dip galvanized per ASTM A123, since these sit in exterior walls.
2. Please revise the bollards to ASTM A53 Gr B Schedule 80 pipe. If Schedule 40 is intended, declare it as a deviation on the cover sheet with the reason so the architect can rule on it.
5. Please remove the blanket field-verify note and dimension from the contract documents; call out any specific conflicts separately.
10. Please add anchorage/embedment details for each item.
Supplier / rep 1 item
4. Please add product data for the shop primer and the ASTM A780 galvanizing repair paint.
Project manager 4 items
6. The spec has this section furnishing these items for the concrete trade to install. Please show them as furnished by Acme.
7. The spec includes concrete fill and crowned tops in this section. Please update the note.
8. Field touch-up of primer and galvanizing is part of this section. Please update the note.
9. Please include current welding certificates with the package.
Engineer of record 1 item
3. Please include the ladder calculations signed and sealed by a PE licensed in the project's state.

8. Specification Compliance Matrix - 05 50 00 Metal Fabrications

Package pages refer to your submittal PDF.

TagSpec Para.RequirementFound in PackageStatusPkg Pages
11.3.AProduct data: post-installed anchorsHilti KB-TZ2 stainless expansion anchor, ESR attachedCOMPLIES1
21.3.AProduct data: nonshrink groutSika Grout 212COMPLIES1
31.3.AProduct data: shop primerNot in packageMISSING-
41.3.AProduct data: galvanizing repair paintNot in packageMISSING-
51.3.BShop drawings with plans, details, connections, anchorage, weld symbolsErection plan and details D1-D4; no anchorage details
Plans and details shown; anchorage details for bollards, ladder and lintels not shown.
REVISE2-6
61.3.CRoof ladder delegated design, signed and sealed by licensed PE'Design by fabricator. (No calculations included.)'
Sheet says 'Design by fabricator. (No calculations included.)'
MISSING5
71.4.AWelding certificatesNot in packageMISSING-
82.2.APlates, shapes, bars ASTM A36Lintels L6x4x3/8 ASTM A36COMPLIES3
92.2.BBollard pipe ASTM A53 Gr B, Schedule 80ASTM A53 Gr B Schedule 40
Schedule 40 shown.
REVISE4
102.2.CTubing ASTM A500 Gr CLadder rails and door framing HSS ASTM A500 Gr CCOMPLIES5-6
112.3.AStainless torque-controlled expansion anchors with ICC-ES reportHilti KB-TZ2 stainless with ICC-ES reportCOMPLIES1
122.5.AExterior items (lintels in exterior walls, bollards, ladder) hot-dip galvanized ASTM A123Bollards and ladder galvanized; lintels shop primed
Bollards and ladder OK; lintels shown shop primed only.
REVISE3-5
132.5.BInterior items shop primedOverhead door supports shop primedCOMPLIES6
142.6.AFurnish anchor bolts and embed plates for overhead door supportsShown as furnished and installed by others
Shops say furnished and installed by others.
REVISE2, 6
Checked and clear
✓ Package: no content that should be removed

9. Scope Check: By Others and Exclusions

ItemShown on SubmittalFurnished By (Spec)Installed ByResult
Overhead door embed plates and anchor bolts
p.2, Sheet E1, Note 6
Furnished and installed by othersThis section (05 50 00), per 2.6.ASection 03 30 00 (concrete), per 1.1.BSCOPE GAP
Bollard concrete fill
p.4, Sheet D2
Concrete fill by othersThis section, per 3.1.AThis section, per 3.1.ASCOPE GAP
Field touch-up of primer and galvanizing
p.6, Sheet D4
Field touch-up by othersThis section, per 3.1.BThis section, per 3.1.BSCOPE GAP

10. Finishes and Coatings

ItemSpec RequiresShownLocation
Lintels L1-L6 in exterior wallsHot-dip galvanized after fabrication, ASTM A123
2.5.A
Shop primed, grayp.3, Sheet D1

11. Dimensions

IssueLocationCD Reference
General Note 4 says 'All dimensions field verify prior to fabrication.' Use the contract document dimensions; only raise specific conflicts.p.2, Sheet E1, Note 4-

12. Package As Received

SecContentsPkg Pages
0
Cover, contents and product data list
1
1
Sheet E1 Erection Plan
2
2
Sheet D1 Lintels
3
3
Sheet D2 Bollards
4
4
Sheet D3 Roof Ladder
5
5
Sheet D4 Overhead Door Supports
6

Content that doesn't apply

Nothing found that should be removed.

13. What This Review Couldn't Check

  1. No contract drawings were provided, so lintel bearing, ladder geometry and bollard heights could not be checked against the CDs.
OneRound pre-flight reviews are a pre-submission quality check. They are not an approval, an engineering review, or a substitute for review by the Architect/Engineer of record.Generated 10/20/2026