Almost every set of shop drawings has a few notes that push work to someone else: "by others," "NIC," "not in contract," "furnished by others," "by GC," "existing." Each one is a quiet claim about scope. When it matches the spec, it's fine. When it doesn't, one of two things happens.
Before a package goes out, list every "by others" note and answer four questions for each.
Copy it word for word, with the sheet and detail. "Embed plates furnished and installed by others" is different from "embed plates installed by others."
Search your section for the item. Specs often have one section furnish an item and another install it. Embeds, anchor bolts, sleeves and frames are the usual examples.
Check your section and the related sections it references. "Furnish for installation under Section 03 30 00" is common language.
If the spec is silent and no trade has it, it's a scope gap. Raise it now, in writing, while it's cheap.
When you find a scope issue on a trade's package, send it in a separate note from the technical corrections. Scope questions can take time to settle, and they shouldn't hold up the drawing fixes. Cite the spec article, keep the tone collaborative, and ask the trade to update the note or explain how they read it differently.
Treat every "by others" note as a promise. If you write it, you should be able to point to the spec article that makes it true. If you can't, change the note before the architect asks you to.
This guide is general information, not legal advice. Your contract and specification govern. AIA and A201 are trademarks of The American Institute of Architects.