The stamp on a returned submittal decides what happens to your schedule. One stamp lets you release fabrication today. Another sends your package back to the start of the line. The wording changes from firm to firm, but the stamps fall into a few groups, and each one calls for a different next move.
| Stamp (common wording) | What it means | Release fabrication? | Resubmit? |
|---|---|---|---|
| No Exceptions Taken / Reviewed / Approved | The reviewer found nothing to change. | Yes, once your GC releases it. | No |
| Make Corrections Noted / Approved as Noted / Reviewed as Noted | Acceptable if you make every correction marked on it. | Yes, with every note built in. | Usually no, unless the stamp or a note asks for it. |
| Amend and Resubmit / Approved as Noted, Resubmit | Mostly acceptable, but the reviewer wants to see the corrections. | Only the parts the reviewer releases, in writing. | Yes |
| Revise and Resubmit | Not acceptable as submitted. The review clock starts over. | No | Yes, the full package |
| Rejected / Not Approved / Submit Specified Item | The product or approach doesn't meet the contract, or needs a substitution request first. | No | Yes, with a compliant product or a proper substitution request |
| For Record Only / Received | Informational submittal filed, with no action taken. | Not a release by itself; check your spec. | No |
Your spec's Division 01 submittal section (usually 01 33 00) defines the exact stamp language and review period on your job. It governs over this table.
Every spec sets its own review period. The federal guide spec, UFGS 01 33 00, defaults to 30 calendar days for government review, and gives each resubmittal "the same" period as the first. It makes the contractor responsible for the extra review time that resubmittals cause, and says no time extensions will be allowed for time lost in late submittals. Check your own spec, but the pattern holds on most jobs: a kickback costs you a full review cycle, not a few days.
Many Revise and Resubmit returns come from things you can check before you send: a finish that doesn't match the spec, a missing calc or certificate, unmarked options on a cut sheet, a "by others" note on your own scope, or a deviation that isn't declared up front. Under the AIA A201 general conditions, the architect's approval doesn't relieve you of a deviation unless you specifically pointed it out when you submitted and it was approved in writing as a minor change, or by Change Order or Construction Change Directive (§3.12.8). The UFGS warns that unflagged variations can mean rejection and removal of the work. Declare deviations on the cover sheet, and the reviewer can accept them on purpose.
Related: "By others": the most expensive two words on a shop drawing · 05 50 00 misc steel submittals: why they get kicked back
This guide is general information, not legal advice. Your contract and specification govern. AIA and A201 are trademarks of The American Institute of Architects.